Prince George Update Apr 01, 2008
- Various Net Down tasks involving general projects and planning development including Footprint update, GIS update and prioritize areas under Multiple Accounts to focus on FG MPB impacted areas
- Preparation of various tender documentation and information for 2008 projects.
- Project and information roll-over from previous project led by NIFR –JS MPB impacted areas (free growing and non-free growing areas)
- Updating Safety Plan (sent to PwC)
- Updating Quality Assurance Plans and related procedures documentation (sent to PwC)
- Finalizing Planting Work Plans and Maps 280ha and 300,000 trees for Summer 2008 (including layout, traversing, mapping, creating and editing Work Plans)
- Finalizing Recce Survey Program of FG impacted opening by MPB, maps and GIS for 15,000 ha for 2008 season
- Finalizing Full Survey Program of FG impacted openings by MPB, maps and GIS for 2,600 ha for 2008 season
- Access Management update for areas under project for 2008
- Initiating First Nations information sharing and consultation process for 2008/2009 projects
- Initiated 11 projects in PINES (currently all pending)
- Continued dialogue and meetings with NIFR staff, Prince George Forest District staff.
|