Arrow TSA
Planning and preparatory work is underway for activities planned for the field season of 2009. First Nations information sharing and AOA review has begun. Planting contracts have been awarded, some DTA contract work has been tendered and awarded.
Pend O’Reille spring planting
Approx 350 K seedlings between April 15-May 15
Springer Creek spring and summer planting
Approx 150 K seedlings between June 1 and July 1
Springer Creek DTA
Approx 150 ha in late May
Approx 250 ha in August/September
Chapleau DTA
Approx 100 ha in August/September
Other projects ongoing for Arrow TSA include:
-impeded file review
-surveys planning: MPB, wildfire, impeded
-review of road needs for operational projects
-RESULTS data entry and updating
-ITSL proposal